City approves a safer-streets redesign by Roxbury's Higginson-Lewis School; 135 Dudley Street found to hang over the sidewalk
The Public Improvement Commission approved the Walnut and Humboldt avenues plan Thursday. Two housing projects, on Dudley Street and in the Fenway, come back for public hearings on Dec. 3.
The Public Improvement Commission, the city board that approves changes to public streets and sidewalks, met for 38 minutes online Thursday. It approved a school-zone redesign in Roxbury and heard two housing projects that come back for votes on Dec. 3.
Approved: Walnut and Humboldt avenues, Roxbury
The commission voted, with no objections and no public comment, to approve a Public Works Department plan for Walnut Avenue, generally between Humboldt Avenue and Martin Luther King Jr. Boulevard, and the Humboldt Avenue intersections nearby (at 0:15:52 in the city's video).
A Public Works engineer told the commission the site is next to the Higginson-Lewis School, where a child was hit by a driver during pickup or drop-off, and that it had also been evaluated for green infrastructure, so the two efforts were combined into an intersection reconstruction (at 0:08:59 in the city's video). The work includes:
- Curb realignment and rebuilt roadway and sidewalks.
- New and relocated curb ramps, raised crosswalks and median islands.
- Traffic signal, street lighting and storm drain work, plus green stormwater infrastructure and fencing.
- A small corner plaza with seating.
- Removal of two speed humps on Walnut Avenue.
Since the commission first saw the plan two weeks ago, the design team added a firmer surface in three narrow tree pits and is considering markers so snowplows don't hit the new curb extensions (at 0:12:24 in the city's video). The city did not give a construction date at the meeting.
Advertisement
Next: 135 Dudley Street, Roxbury
Cruz Development Corporation and the Mayor's Office of Housing have joint petitions for a rental building at 135 Dudley Street, at Washington Street. They were back as new business instead of at a public hearing because of a problem with the required newspaper notice, the project's engineer said; the hearing is now set for Dec. 3 (at 0:17:12 in the city's video).
The engineer said a last-minute title search found that the building, as laid out, sat partly on the city's sidewalk. The first floor was pulled back onto the property, but upper floors still extend over the public way, in a two-foot sliver and a larger 7.8-foot section, so the project needs a "vertical discontinuance" of that air space (at 0:28:06 in the city's video). A city official said the value of the air space is being worked out with Cruz and the housing office.
Other parts of the plan:
- Residents would drive in from Dudley Street through a 20-foot two-way driveway. A separate one-way driveway off Washington Street would be for trash, deliveries and moving trucks (at 0:23:18 in the city's video).
- The developer agreed to rebuild a cracked curb ramp across Dudley Street after the Disabilities Commission flagged it, and moved sewer work out from under a tree canopy after a Parks Department request (at 0:18:32 in the city's video).
- An old Verizon telephone cabinet behind a ramp narrows the sidewalk; the engineer said Verizon wants the developer to pay to move it (at 0:25:25 in the city's video).
A commissioner asked who is clearing snow on the Dudley Street sidewalk this winter; the team said it would have an answer by Dec. 3 (at 0:26:46 in the city's video).
Advertisement
Next: 112 Queensberry Street, Fenway
Fenway Forward, formerly Fenway Community Development Corporation, described 112 Queensberry Street as a new 24-unit rental building, all of it affordable. Its petition covers a rebuilt sidewalk, curb changes, a modified driveway, two bike racks and replacing one street tree, which went through a tree hearing on Oct. 1 with no opposition. The developer said the sidewalk's clear path would be 7.6 to 8.87 feet wide, and that it is aiming to close financing and begin construction toward the end of the summer (at 0:32:51 in the city's video). Its public hearing is also Dec. 3.
How to weigh in
The commission usually meets online on Thursday mornings; members of the public can use Zoom's raise-hand feature to comment. Agendas are on the city's Legistar calendar.