Cummins Highway is done, and the city says fast drivers fell from 30% to 7%. Here's the rest of Boston's 2026 street work
A city release tallies the construction season: 51 miles repaved, 1,946 curb ramps, 7,582 street lights. What it doesn't list is what got delayed.
The $28 million rebuild of Cummins Highway in Mattapan is finished, and the city says drivers have slowed down: the share going 35 mph or faster fell from 30% in 2018 to 7% in 2026, according to a city release published Thursday that also tallies the year's street work across Boston.
The release came the same week the City Council held its hearing on an ordinance that would require a yearly public report on every street project (our story). Interim Chief of Streets Chris Osgood told councilors that the Cummins Highway ribbon cutting was one of the ways the city reports on its work now.
Cummins Highway
The project runs from Fairway Street to the intersection of Harvard Street and Wood Avenue. The city says the old four-lane design "made speeding easier" and that the street had two fatal crashes since 2015. The rebuild added:
- New sidewalks, curb ramps, street lighting and traffic signals.
- Sidewalk-level bike lanes, improved bus stops, street trees and green stormwater infrastructure.
- A roundabout at the three-way intersection at Greenfield Road.
McCourt Construction was the general contractor. City Councilor Enrique Pepén said in the release that "for too long, drivers treated Cummins like a highway and not the neighborhood connector it is." The next project nearby is Wood Avenue, which connects Cummins Highway to River Street; construction is expected to start in spring 2027, the city says.
Advertisement
The year's totals
The city's figures for 2026, from the release:
- Resurfacing: 51 miles of roadway, up from 50 in 2025.
- Curb ramps: 1,946 rebuilt to ADA standards, up from 1,723.
- Potholes: 5,860 filled.
- Street lights: 7,582 fixtures replaced, nearly three times the 2,483 in 2025 and the most since 2016. The city says its own crews did the work for about a third of what outside contractors would cost.
- Markings: more than 60 miles of crosswalks and 26 miles of center lines.
- Signals and signs: 3,365 signal repair calls in fiscal 2026 and 5,078 signs installed as of October.
- Parking meters: more than 5,600 old meters replaced with 1,000 pay-by-plate meters.
- Bluebikes: 16 new stations, 33 replaced and 780 e-bikes added.
The release doesn't list how many projects were paused or delayed this year, or what they cost. That is the kind of information the council's ordinance (docket 1415) would require.
Other projects named
Completed, according to the city: traffic calming in Charlestown's Lost Village, paid for by the Massachusetts Gaming Commission; Harrison Avenue at the Ink Block, between Herald and East Berkeley streets; the Thoreau Path in the West End; and Reddy Avenue.
Under construction:
Advertisement
- Ellis Elementary Safe Routes to School, Roxbury: traffic calming at six intersections, paid for by a MassDOT grant.
- Jones Avenue, Ballou Avenue and nearby streets: due in 2027.
- Lower Roxbury safety improvements: paid for with federal pandemic relief money, due in spring 2027.
- A Street, Congress Street and Sleeper Street, Fort Point: Sleeper Street work through the winter, finishing in spring 2027 ahead of Congress Street.
In design: Rutherford Avenue and Sullivan Square, where the city submitted 25% plans to MassDOT in May and plans to return to the community by the end of the year; Andrew Square; and the Bennington and Saratoga safety project.
Where to look
The project tracker on the Streets Cabinet's web page lists about 30 projects, Osgood told the council. The council's working session on the reporting ordinance is Dec. 3.